Latest topics
Top posters
| engrjhez® | ||||
| RDV @ GPPPI | ||||
| sunriser431 | ||||
| riddler | ||||
| Ligaw na Binatog | ||||
| Niwram | ||||
| amang'65 | ||||
| charlie brown | ||||
| fe a. araya | ||||
| msm326 |
liquidated damages
Philippine Government Procurement :: RA 9184 Implementing Rules and Regulations Part A (IRR-A) :: Contract Implementation
Page 2 of 2 • Share •
Page 2 of 2 •
1, 2
Re: liquidated damages
jun b wrote:re : computation of liquidated damages. You have different views sir amang and sir ruel. whats the exact formula, gentlemen. Thanks to both of you.
Clause 9.1 of the Special Conditions of the Contract under the old PBD. (This is for Infrastructure only.
Liquidated damages is equivalent to an amount to be determined in accordance with the following formula until the work is completed and accepted or taken over by the PROCURING ENTITY:
TLD = VUUP x [ (1+ OCC)n - 1] x K
VUUP = TCP – VCUP
WHERE:
TLD = Total Liquidated Damages, In Pesos
VUUP = value of the uncompleted and unusable portions of the contract work, as of the expiry date of the contract, in pesos
TCP = Total Contract Price, In Pesos
VCUP = value of the completed and usable portion of the contract work, as of the expiry date of the contract, in pesos
OCC = prevailing opportunity cost of capital for government projects set by NEDA, which is currently pegged at 15%
n = total number of years that the contract work is delayed after the expiry date of the contract
K = adjustment factor to cover additional losses
= 1 + C + ( i x n)
WHERE:
C = cost of construction supervision as a percentage, not exceeding 10%, of construction cost
i = annual inflation rate as defined by NEDA
The Head of the PROCURING ENTITY may also impose additional liquidated damages on the contractor provided such is prescribed in the Instructions to Bidders.
A project or a portion thereof may be deemed usable when it starts to provide the desired benefits as certified by the targeted end-users and the concerned PROCURING ENTITY.
To be entitled to such liquidated damages, the PROCURING ENTITY does not have to prove that it has incurred actual damages. Such amount shall be deducted from any money due or which may become due the contractor under the contract and/or collect such liquidated damages from the retention money or other securities posted by the contractor whichever is convenient to the PROCURING ENTITY.
In case that the delay in the completion of the work exceeds a time duration equivalent to ten percent (10%) of the specified contract time plus any time extension duly granted to the contractor, the procuring entity concerned may rescind the contract, forfeit the contractor’s performance security and takeover the prosecution of the project or award the same to a qualified contractor through negotiated contract.
In no case however, shall the total sum of liquidated damages exceed ten percent (10%) of the total contract price, in which event the contract shall automatically be taken over by the procuring entity concerned or award the same to a qualified contractor through negotiation and the erring contractor’s performance security shall be forfeited. The amount of the forfeited performance security shall be aside from the amount of the liquidated damages that the contractor shall pay the government under the provisions of this clause and impose other appropriate sanctions.
Section 68. Liquidated Damages of the New rules for infra and goods
All contracts executed in accordance with the Act and this IRR shall contain a provision on
liquidated damages which shall be payable by the contractor in case of breach thereof. For
the procurement of goods, infrastructure projects and consulting services, the amount of the
liquidated damages shall be at least equal to one-tenth of one percent (0.1%) of the cost of
the unperformed portion for every day of delay. Once the cumulative amount of liquidated
damages reaches ten percent (10%) of the amount of the contract, the procuring entity
shall rescind the contract, without prejudice to other courses of action and remedies open to it.
x x x x x
77.2. In cases where the advertisements or invitations for bids were issued before the
effectivity of this IRR, Procuring Entities may continue adopting the procurement
procedures, rules, and regulations provided in the IRR Part A or other applicable
laws, as the case may be.(a)]
Since the project is already overtaken by a new IRR, needless to say but to abide what is stipulated in our Old Contract

riddler- Board Veteran

-
Number of posts: 475
Company/Agency: lgu
Occupation/Designation: engineer
Registration date: 2009-03-03
Re: liquidated damages
What I mean is you have different views on what formula shall be used in our computation of the LD the old or the new. You said we could not change the horse in the middle of the race while sir amang said the new since the old has been superseded. Thanks again

jun b- New Member

-
Number of posts: 10
Age: 52
Company/Agency: NIA-SURIGAO DEL SUR IMO
Occupation/Designation: BAC Chairman
Registration date: 2009-09-16
Re: liquidated damages
jun b wrote:What I mean is you have different views on what formula shall be used in our computation of the LD the old or the new. You said we could not change the horse in the middle of the race while sir amang said the new since the old has been superseded. Thanks again
i am sorry jun i did not notice that the procedings you used was that of the old irr, because you said "a certain contract was awarded making use of the old irr.." ruel is right you have to stick to the old irr in computing your LD.

amang'65- Valued Contributor

-
Number of posts: 248
Company/Agency: City of Baguio
Occupation/Designation: sekretarya
Registration date: 2009-09-19
Re: liquidated damages
thanks sir amang for the clarification.

jun b- New Member

-
Number of posts: 10
Age: 52
Company/Agency: NIA-SURIGAO DEL SUR IMO
Occupation/Designation: BAC Chairman
Registration date: 2009-09-16
Re: liquidated damages
something is wrong with the "engine" today. my replies are posted repeatedly.. i thought the previous ones were not "gobbled up" by the engine.. i hope the "forum manager" can do something to erase the repititions... salamat.

riddler- Board Veteran

-
Number of posts: 475
Company/Agency: lgu
Occupation/Designation: engineer
Registration date: 2009-03-03
Re: liquidated damages
by the way sir ruel what is now the annual inflation rate as defined by NEDA, for us to compute the LD based on the old IRR

jun b- New Member

-
Number of posts: 10
Age: 52
Company/Agency: NIA-SURIGAO DEL SUR IMO
Occupation/Designation: BAC Chairman
Registration date: 2009-09-16
Re: liquidated damages
jun b wrote:by the way sir ruel what is now the annual inflation rate as defined by NEDA, for us to compute the LD based on the old IRR
mwuaaah! that i do not know
perhaps you can surf into the website of NEDA or DTI. 
riddler- Board Veteran

-
Number of posts: 475
Company/Agency: lgu
Occupation/Designation: engineer
Registration date: 2009-03-03
Re: liquidated damages
For purpose of Discussion
Since the LD will definitely form part of the BAC Funds, can this be shared with the Inspection Committee Team? considering they are the ones computing, imposing this provision.
Since the LD will definitely form part of the BAC Funds, can this be shared with the Inspection Committee Team? considering they are the ones computing, imposing this provision.

sunriser431- Elite Poster

-
Number of posts: 825
Company/Agency: Goccs/Jolo Sulu The Land I call my Home
Occupation/Designation: IAS
Registration date: 2009-05-07
Re: liquidated damages
sunriser431 wrote:For purpose of Discussion
Since the LD will definitely form part of the BAC Funds, can this be shared with the Inspection Committee Team? considering they are the ones computing, imposing this provision.
Sunriser431:
Liquidated Damages collected or imposed by the procuring entity do not form part of "BAC Funds."
RDV
Page 2 of 2 •
1, 2
Permissions of this forum:
You cannot reply to topics in this forum





» L G U Kapangan BAC Posting
» What is an SAA?
» Are there instances where competitive bids can specify a specific make of a product?
» 20 % BARANGAY DEVELOPMENT FUND
» DPWH cancels 19 ‘midnight deals’ worth over P934M
» Live streaming of Marikina public bidding on Internet set
» Procurement of Infrastructure
» Delicadeza...?
» Eligibility Criteria of bidder under Infrastructure Project