Request for Quotation
Page 1 of 1 • Share •
Request for Quotation
On the sample form, the signatory in the request for quotation is the Procurement Officer. in our practice, the BAC Chair sign the requests for quotation since the manual for LGUs states that "For Shopping under Section 52 (b) of the IRR-A, the BAC, through the BAC
Secretariat, issues Requests for Quotation to at least three (3) suppliers in good
standing." Should the secretariat sign the requests for quotations???
Secretariat, issues Requests for Quotation to at least three (3) suppliers in good
standing." Should the secretariat sign the requests for quotations???
Re: Request for Quotation
Please be reminded that both sample forms and the LGU manual are referring to IRR-A which was already amended by the Revised IRR. In addition, the GPPB issued guidelines on Shopping and Small Value Procurement last December 2009. To me, it is always substance over form. But whoever signs the RFQ must be duly authorized by the HOPE.
Re: Request for Quotation
Bernadette G. Driza wrote:On the sample form, the signatory in the request for quotation is the Procurement Officer. in our practice, the BAC Chair sign the requests for quotation since the manual for LGUs states that "For Shopping under Section 52 (b) of the IRR-A, the BAC, through the BAC
Secretariat, issues Requests for Quotation to at least three (3) suppliers in good
standing." Should the secretariat sign the requests for quotations???
For us GOCCs its the BAC chairman who normally sign this RFQ, so in the event any request for clarification in the bids can be directed to the BAC. :bounce:Hope this would be of help.

sunriser431- Board General

-
Number of posts: 669
Company/Agency: Goccs/Jolo Sulu The Land I call my Home
Occupation/Designation: Head Procurement/Head Secretariat
Registration date: 2009-05-07
Re: Request for Quotation
The purpose of having a BAC and HOPE is for check and balances, if the BAC Chair will be the approving or duly authorized representative of the HOPE then there will be violation of the principle on check and balances. The duly authorized representative must be other than BAC members.
_________________
Each candidate behaved well in the hope of being judged worthy of election. However, this system was disastrous when the city had become corrupt. For then it was not the most virtuous but the most powerful who stood for election, and the weak, even if virtuous, were too frightened to run for office.
- Niccolo Machiavelli

Pritong Kandule- Valued Contributor

-
Number of posts: 280
Company/Agency: Gobyerno ng Pilipinas
Occupation/Designation: Ordinaryong Empleyado
Registration date: 2009-10-06
Re: Request for Quotation
Thank you po for the opinions. juz wondring po if we are conforming to the the existing rules, since silent nman ang revised IRR who will sign the requests for quotation.
Eniwe po thank you very much...
Eniwe po thank you very much...
Re: Request for Quotation
11.2.5. In no case shall the Head of the Procuring Entity and/or the approving authority be the Chairman or a member of the BAC.
12.1. The BAC shall have the following functions: (j) recommend award of contracts to the Head of the Procuring Entity or his duly authorized representative:
There is no direct provision in the revised IRR pertaining to the person who has authority to sign the RPQ however the above provisions, we could assume that generally the BAC is responsible with all procurement. and Second the BAC only has the power to recommend.
12.1. The BAC shall have the following functions: (j) recommend award of contracts to the Head of the Procuring Entity or his duly authorized representative:
There is no direct provision in the revised IRR pertaining to the person who has authority to sign the RPQ however the above provisions, we could assume that generally the BAC is responsible with all procurement. and Second the BAC only has the power to recommend.
Last edited by Pritong Kandule on Tue Feb 16, 2010 1:27 pm; edited 1 time in total
_________________
Each candidate behaved well in the hope of being judged worthy of election. However, this system was disastrous when the city had become corrupt. For then it was not the most virtuous but the most powerful who stood for election, and the weak, even if virtuous, were too frightened to run for office.
- Niccolo Machiavelli

Pritong Kandule- Valued Contributor

-
Number of posts: 280
Company/Agency: Gobyerno ng Pilipinas
Occupation/Designation: Ordinaryong Empleyado
Registration date: 2009-10-06
Request for Quotation
As i understand po kase, before you can recommend award, just like with the comp. public bidding, you should determine who has the lowest and most responsive bid. in case of shopping, the bac should request for quotations and recommend the supplier with the lowest quotation. that's why, in our case, we prepare abstract of quotations duly signed by the BAC (chair and members.) 
Last edited by Bernadette G. Driza on Wed Feb 10, 2010 2:46 pm; edited 2 times in total (Reason for editing : mali)
Re: Request for Quotation
Bernadette G. Driza wrote:As i understand po kase, before you can recommend award, just like with the comp. public bidding, you should determine who has the lowest and most responsive bid. in case of shopping, the bac should request for quotations and recommend the supplier with the lowest quotation. that's why, in our case, we prepare abstract of quotations duly signed by the BAC (chair and members.)
You have a point there Bernadette. We should take note that the check and balance required here is that the recommending should not be the approving official. In the case of the RFQ, it is only a request for quotation which is similar to an invitation to bid (which is signed by the BAC Chair). While the IRR has been revised which would necessitate corresponding revisions in the GPM, we cant be sure yet if this particular procedure will be revised considering that the IRR revisions did not alter the basic premise of the check and balance.
I have been searching for a standard form for the RFQ taking into account the revisions under res 09-2009 with no luck as yet. In the meantime i think we could use the signatories as prescribed under the GPM

charlie brown- Active Poster

-
Number of posts: 130
Company/Agency: national government
Occupation/Designation: BAC Chair
Registration date: 2010-01-13
Re: Request for Quotation
I will just be sharing our ideas here and on some roll out seminars conducted by the accredited Regional Trainers din....
May I ask do you have a procuring unit (GSD/GSO)?
Basta Shopping/SVP there are new guidelines and threshold based on the Revised IRR as you guide.
Basically some of the functions stipulated on RA 9184 is under this department and in our case I take my stand to avoid confusions and miscommunication on other units/departments and work well for us...in addition I don't receive AOMs particularly on procurement related transactions....
I always browse opinions of fellow forum members ....
ang importante sa atin mga LGU walang natatapakan at di nilampas sa unit or work ng iba.....
msm326
May I ask do you have a procuring unit (GSD/GSO)?
Basta Shopping/SVP there are new guidelines and threshold based on the Revised IRR as you guide.
Basically some of the functions stipulated on RA 9184 is under this department and in our case I take my stand to avoid confusions and miscommunication on other units/departments and work well for us...in addition I don't receive AOMs particularly on procurement related transactions....
I always browse opinions of fellow forum members ....
ang importante sa atin mga LGU walang natatapakan at di nilampas sa unit or work ng iba.....
msm326

msm326- Active Poster

-
Number of posts: 137
Company/Agency: LGU SANTA CRUZ
Occupation/Designation: MUNICIPAL GENERAL SERVICES OFFICE
Registration date: 2009-06-03
Re: Request for Quotation
For msm326. Yes po, we have GSO. Actually po we have 2 procurement units. our lce created another procurement unit for infra projects since our gso is overload with other procurements and our lce needs immediate action esp. on infra projects.
i wish we could have the sample forms...
i wish we could have the sample forms...
Re: Request for Quotation
Bernadette G. Driza wrote:For msm326. Yes po, we have GSO. Actually po we have 2 procurement units. our lce created another procurement unit for infra projects since our gso is overload with other procurements and our lce needs immediate action esp. on infra projects.
i wish we could have the sample forms...
Insofar as the RFQ I just modified our existing form in the meantime and incorporated all the suggestion in the guidelined for SVP.

charlie brown- Active Poster

-
Number of posts: 130
Company/Agency: national government
Occupation/Designation: BAC Chair
Registration date: 2010-01-13
Permissions of this forum:
You cannot reply to topics in this forum








» emergency purchases
» Prebid Conference and Opening
» Submission of LOI
» Non-Payment of 10% Retention Fee
» Hiring of US-Based Lobby and Law Firm
» new "STRIKE THREE" ruling based on revised IRR?
» Addendum or amendments to the revised IRR of RA 9184
» award or not to award
» Contract extension of security services