This was taken from the shoutbox of GPPB home page:
Glaiza Ecleo
I am a liaison of a construction firm in Bicol, I just would like to know if ever we does not attached the Bid Bulletin in our technical documents, could it be a ground for our disqualification?

This was already answered in this topic.

And the answer is NO. Smile
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2480
Age : 39
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

Re: Non-Submission of Bid Bulletin

Post by charlie brown on Thu Oct 07, 2010 4:44 pm

engrjhez® wrote:This was taken from the shoutbox of GPPB home page:
Glaiza Ecleo
I am a liaison of a construction firm in Bicol, I just would like to know if ever we does not attached the Bid Bulletin in our technical documents, could it be a ground for our disqualification?

This was already answered in this topic.

And the answer is NO. Smile

not attaching the bid bulletins in the bid may not be a ground for disqualification but failure to comply with any amendments provided therein could be. what im saying is that the supplier could not use as an excuse that he was not aware of the amendments if any, for not complying with the requirements
avatar
charlie brown
Valued Contributor
Valued Contributor

Male Number of posts : 218
Company/Agency : national government
Occupation/Designation : BAC Chair
Registration date : 2010-01-13

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum