good morning, everyone. may i know who approves the request of the supplier to extend the delivery period? Is it the BAC or the HOPE? are there any limitations on the request of the bidder? ( i mean, is the bidder allowed to request only once?)
thank you.
thank you.

misty- Active Poster

-
Number of posts: 68
Company/Agency: lgu
Occupation/Designation: finance
Registration date: 2009-06-08
Re: approval of extension of the delivery period
misty wrote:good morning, everyone. may i know who approves the request of the supplier to extend the delivery period? Is it the BAC or the HOPE? are there any limitations on the request of the bidder? ( i mean, is the bidder allowed to request only once?)
thank you.
It is already the HOPE or his/her duly authorized official, and no longer the BAC, who will approve requests for extensions of delivery period after the contract has already been signed.
There is no limitation on the number of requests for extension. The contract provision that would cover extension of delivery period is Item 18.2 of the GCC, to wit:
"If at any time during the performance of this Contract, the Supplier or its subcontractor(s) should encounter conditions impending timely delivery of the Goods and/or performance of Services, the Supplier shall promptly notify the Procuring Entity in writing of the fact of the delay, its likely duration and its cause(s). As soon as practicable after receipt of the Supplier's notice, and upon causes provided for under GCC Clause 22, the PE shall evaluate the situation and may extend the Supplier's time for performance, in which case the extension shall be ratified by the parties by amendments of Contract."
For those delays in the performance not covered by approved extensions, the provisions for Liquidated Damages will apply.
Re: approval of extension of the delivery period
misty wrote:xxxx are there any limitations on the request of the bidder? ( i mean, is the bidder allowed to request only once?). xxxx
opinion of the GPPB, try this LINK

sunriser431- Elite Poster

-
Number of posts: 1483
Company/Agency: Goccs Jolo Sulu All the way Downsouth
Occupation/Designation: IAS
Registration date: 2009-05-07
Re: approval of extension of the delivery period
much thanks to you both, sir rdv and sunriser431

misty- Active Poster

-
Number of posts: 68
Company/Agency: lgu
Occupation/Designation: finance
Registration date: 2009-06-08
Re: approval of extension of the delivery period
misty wrote:much thanks to you both, sir rdv and sunriser431
you are welcome "misty".

sunriser431- Elite Poster

-
Number of posts: 1483
Company/Agency: Goccs Jolo Sulu All the way Downsouth
Occupation/Designation: IAS
Registration date: 2009-05-07
Similar topics» Delivery service
» approval of extension of the delivery period
» Maximun Delivery Period Allowed
» Sample Form (proposed Canvass Committee)
» Extension of period allowed for repeat order
» approval of extension of the delivery period
» Maximun Delivery Period Allowed
» Sample Form (proposed Canvass Committee)
» Extension of period allowed for repeat order
Philippine Government Procurement :: RA 9184 Revised Implementing Rules and Regulations :: Procurement Related Activities
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
» BAC/TWG member
» RE: New Philgeps website address
» Re: ABC for Security and Janitorial Services
» re-allignment of budget of APP for other matters.
» Posting@PhilGeps Website
» certificate of site inspection
» LEASE OF PROPERTY
» variation order, negotiated procurement
» Punchlisting