GPPB guidelines for issuing variation order beyond 10%
What are the guidelines to be determined by GPPB for issuing variation order beyond 10%?

leobcaleja- New Member

-
Number of posts: 19
Company/Agency: hanjin heavy industries and const. co., ltd.
Occupation/Designation: chief office engineer
Registration date: 2010-09-19
Re: GPPB guidelines for issuing variation order beyond 10%
leobcaleja wrote:What are the guidelines to be determined by GPPB for issuing variation order beyond 10%?
There is none. Procuring Entities are not allowed to enter into variation orders exceeding 10% consistent with prevailing COA guidelines.
Re: GPPB guidelines for issuing variation order beyond 10%
The authority of the COA to concur with the contracts (for infra projects) covering variation orders within and in excess of 25% ceiling as provided in COA Circular No. 81-101 had been repealed by COA Circular No. 82-195. Please correct me if I’m wrong Engrjhez, but I am not aware of any COA guidelines prohibiting variation orders in excess of 10% of the original contract cost. The function of the COA is only to review (both as to legal and technical aspects) contracts covering such variation orders exceeding the 10% ceiling.
I think, par. 1.4 of the Annex “E” of the revised IRR provides that the GPPB shall determine (issue, if I may say so) the guidelines for positive variation orders which go beyond the 10% but not more than 20% of the original contract price.
Thanks and peace.
BTW, is there a way to block irrelevant posts such as those posted by aobama52? it is already irritating.
I think, par. 1.4 of the Annex “E” of the revised IRR provides that the GPPB shall determine (issue, if I may say so) the guidelines for positive variation orders which go beyond the 10% but not more than 20% of the original contract price.
Thanks and peace.
BTW, is there a way to block irrelevant posts such as those posted by aobama52? it is already irritating.
Mikel- Active Poster

-
Number of posts: 64
Company/Agency: Gobyerno ng Pilipinas
Occupation/Designation: Empleyado
Registration date: 2009-03-11
Re: GPPB guidelines for issuing variation order beyond 10%
Thanks for clarifying that Mikel. Now I recalled, it was when contract prices go beyond 10% when the COA issues (as on our case) a notification of apparent overpricing. But even though, I will still look at it again (and probably do some research again) because I knew I have read sometime limits on allowable variation orders.
Re: GPPB guidelines for issuing variation order beyond 10%
In Section 53.4 of the revised IRR states that the amount involved should not exceed the amount of the on-going project. Can this be considered as the maximum limit for issuing variation order or supplemental contract agreement? At this stage, who approves the variation order/supplemental agreement if the procuring entity is a GCOC?

leobcaleja- New Member

-
Number of posts: 19
Company/Agency: hanjin heavy industries and const. co., ltd.
Occupation/Designation: chief office engineer
Registration date: 2010-09-19
Re: GPPB guidelines for issuing variation order beyond 10%
Sec. 53.4 contemplates a separate contract for a separate project, independent and distinct from the original project, although these projects are adjacent and contiguous to each other. To my understanding, a variation order or supplemental agreement shall be made or issued only for one and the same project, thus, sec. 53.4 is not applicable to variation orders or supplemental contracts.
Mikel- Active Poster

-
Number of posts: 64
Company/Agency: Gobyerno ng Pilipinas
Occupation/Designation: Empleyado
Registration date: 2009-03-11
Re: GPPB guidelines for issuing variation order beyond 10%
Does COA have threshold or guidelines on the mark-ups for cost plus basis payments?

leobcaleja- New Member

-
Number of posts: 19
Company/Agency: hanjin heavy industries and const. co., ltd.
Occupation/Designation: chief office engineer
Registration date: 2010-09-19
Similar topics» Eskimo Ball (Kickball Variation)
» GPPB guidelines for issuing variation order beyond 10%
» whether Variation Order/Change Order/Extra Work Order applies to consultancy service contract
» variation order
» Looking for GPPB guidelines for procurement agent
» GPPB guidelines for issuing variation order beyond 10%
» whether Variation Order/Change Order/Extra Work Order applies to consultancy service contract
» variation order
» Looking for GPPB guidelines for procurement agent
Philippine Government Procurement :: RA 9184 Implementing Rules and Regulations Part A (IRR-A) :: Contract Implementation
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
» BAC/TWG member
» RE: New Philgeps website address
» Re: ABC for Security and Janitorial Services
» re-allignment of budget of APP for other matters.
» Posting@PhilGeps Website
» certificate of site inspection
» LEASE OF PROPERTY
» variation order, negotiated procurement
» Punchlisting