Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
sir.. good day po..
paki clarify lang po itong section po sa revised irr about PhilGEPS po..
thanks po..
"Section 8.5.3. Registered bidders determined to be eligible may submit their bids at any time
before the closing date specified in the Bidding Documents. The PhilGEPS shall
bar all incoming bids after such date."
tanong ko lang po kung ano pong closing po..
thanks po..
paki clarify lang po itong section po sa revised irr about PhilGEPS po..
thanks po..
"Section 8.5.3. Registered bidders determined to be eligible may submit their bids at any time
before the closing date specified in the Bidding Documents. The PhilGEPS shall
bar all incoming bids after such date."
tanong ko lang po kung ano pong closing po..
thanks po..
stephen- New Member

-
Number of posts: 34
Company/Agency: DepEd
Occupation/Designation: twg
Registration date: 2011-04-01
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
stephen wrote:sir.. good day po..
paki clarify lang po itong section po sa revised irr about PhilGEPS po..
thanks po..
"Section 8.5.3. Registered bidders determined to be eligible may submit their bids at any time
before the closing date specified in the Bidding Documents. The PhilGEPS shall
bar all incoming bids after such date."
tanong ko lang po kung ano pong closing po..
thanks po..
Good day, too, stephen.
The "closing date" being referred to in that particular section of the IRR you quoted refers to the bid closing date. However, up to this time, electronic bid submission through the PhilGEPS is still not possible. Hopefully, it will be implemented before the year ends. In the meantime, we have to make do with manual bid submission.
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
thanks po sir.. mabuhay po kayo..
stephen- New Member

-
Number of posts: 34
Company/Agency: DepEd
Occupation/Designation: twg
Registration date: 2011-04-01
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
Sir RDV,
If a bidder submitted a list on completed, ongoing projects similar in nature, but did not include the necessary attachments to check those on the list, can the BAC disqualify the bidder?
Thanks for your help...
If a bidder submitted a list on completed, ongoing projects similar in nature, but did not include the necessary attachments to check those on the list, can the BAC disqualify the bidder?
Thanks for your help...

eagerlearner- New Member

-
Number of posts: 18
Company/Agency: fhi
Occupation/Designation: bdo
Registration date: 2010-11-27
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
eagerlearner wrote:xxxx
If a bidder submitted a list on completed, ongoing projects similar in nature, but did not include the necessary attachments to check those on the list, can the BAC disqualify the bidder?
Thanks for your help...
Excerpts from the "Statement of Compliance" of the PBDs, which is self explanatory.
xxxxxx.
A statement that is not supported by evidence or is subsequently found to be contradicted by the evidence presented will render the Bid under evaluation liable for rejection. A statement either in the Bidders statement of compliance or the supporting evidence that is found to be false either during Bid evaluation, post-qualification or the execution of the Contract may be regarded as fraudulent and render the Bidder or supplier liable for prosecution subject to the provisions of ITB Clause 3.1(a)(ii) and/or GCC Clause 2.1(a)(ii).

sunriser431- Elite Poster

-
Number of posts: 1483
Company/Agency: Goccs Jolo Sulu All the way Downsouth
Occupation/Designation: IAS
Registration date: 2009-05-07
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
What about if the Bidder did not include all completed contracts, Can the BAC disqualify the Bidder? on what ground?
arsbib- New Member

-
Number of posts: 14
Company/Agency: Bacacay, Albay
Occupation/Designation: BAC Chairman
Registration date: 2011-08-31
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
arsbib wrote:What about if the Bidder did not include all completed contracts, Can the BAC disqualify the Bidder? on what ground?
If the bidder did not submit a statement of on-going and completed government and private contracts (relevant) with its attachments or proofs as indicated in the ITB, then they should be rated FAILED. Reason: they failed the non-discretionary eligibility check.
Re: Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
how to register in the philgeps, I am just new in this just starting my own business

rommelmedel- New Member

-
Number of posts: 1
Company/Agency: Oxhorn Enterprises
Occupation/Designation: manager
Registration date: 2011-09-16
Similar topics» Free IELTS extended essay writing task submission
» Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
» Eligibility Requirements
» Fixed Eligibility Requirements for Alternative Methods of Procurement
» ELIGIBILITY REQUIREMENTS SUBMITTED FAILED DUE TO ERRONEOUS TYPING ERROR
» Registration, Eligibility Requirements and Submission of Bids under the PhilGEPS
» Eligibility Requirements
» Fixed Eligibility Requirements for Alternative Methods of Procurement
» ELIGIBILITY REQUIREMENTS SUBMITTED FAILED DUE TO ERRONEOUS TYPING ERROR
Philippine Government Procurement :: RA 9184 Revised Implementing Rules and Regulations :: Procurement Methods :: Competitive Bidding
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum

» BAC/TWG member
» RE: New Philgeps website address
» Re: ABC for Security and Janitorial Services
» re-allignment of budget of APP for other matters.
» Posting@PhilGeps Website
» certificate of site inspection
» LEASE OF PROPERTY
» variation order, negotiated procurement
» Punchlisting