Post by ikuz23 on Sat Jun 04, 2011 7:46 am

is there a minimum & maximum no. of days for the LGU to release payment after delivery? for the BAC process, the IRR says we have a minimum of 28CD & a maximum of 124CD to release / issue a Notice to Proceed to wining bidder. but how about the payment?
avatar
ikuz23
Active Poster
Active Poster

Male Number of posts : 148
Company/Agency : LGU-Tacurong
Occupation/Designation : Karaniwang empleyado
Registration date : 2011-05-03

Back to top Go down

Re: payment terms

Post by engrjhez® on Sat Jun 04, 2011 10:24 am

ikuz23 wrote:is there a minimum & maximum no. of days for the LGU to release payment after delivery? for the BAC process, the IRR says we have a minimum of 28CD & a maximum of 124CD to release / issue a Notice to Proceed to wining bidder. but how about the payment?

Payment shall be immediately processed upon actual delivery and receipt of items. I believe we all have our CITIZEN'S CHARTER right? Some have the (PMS)OPES REFERENCE TABLES to guide our standard actions. The guiding principles of RA.6713 and RA.9485 shall be our platform in executing both internal and external services.

In short, payment needs be processed with 5 days (provided that it has complete documentation and requirements). Smile
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2480
Age : 39
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

Re: payment terms

Post by ikuz23 on Mon Jun 06, 2011 2:45 pm

tnx engrjhez
avatar
ikuz23
Active Poster
Active Poster

Male Number of posts : 148
Company/Agency : LGU-Tacurong
Occupation/Designation : Karaniwang empleyado
Registration date : 2011-05-03

Back to top Go down

Re: payment terms

Post by sunriser431 on Wed Jul 27, 2011 7:49 pm

engrjhez® wrote:
ikuz23 wrote:is there a minimum & maximum no. of days for the LGU to release payment after delivery? for the BAC process, the IRR says we have a minimum of 28CD & a maximum of 124CD to release / issue a Notice to Proceed to wining bidder. but how about the payment?

Payment shall be immediately processed upon actual delivery and receipt of items. I believe we all have our CITIZEN'S CHARTER right? Some have the (PMS)OPES REFERENCE TABLES to guide our standard actions. The guiding principles of RA.6713 and RA.9485 shall be our platform in executing both internal and external services.

In short, payment needs be processed with 5 days (provided that it has complete documentation and requirements). Smile
Nothing to do with procurement law, Smile To engrjhez, is the (PMS)OPES suspended its application by the CSC? please update. Thanks in advance. bounce
avatar
sunriser431
Grand Master
Grand Master

Male Number of posts : 1518
Company/Agency : Goccs Jolo Sulu All the way Downsouth
Occupation/Designation : IAS
Registration date : 2009-05-07

Back to top Go down

Re: payment terms

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum