Latest topics
» No Objection Letter
Sat Dec 16, 2017 5:21 pm by zeph03

» CATERING SERVICES FOR CONGRESSIONAL MEET AT SAGBAYAN, BOHOL
Thu Dec 14, 2017 7:14 pm by btorres4

» PURCHASE OF FERTILIZERS FOR LIVESTOCK, CORN, HVCDP, INLAND FISHERY, AND ORGANIC PROGRAM
Thu Dec 14, 2017 4:35 pm by btorres4

» Newspaper Publication
Thu Dec 14, 2017 4:10 pm by btorres4

» RENTAL OF LIGHTS AND SOUND SYSTEM
Thu Dec 14, 2017 3:46 pm by btorres4

» Newspaper Publication
Wed Dec 13, 2017 9:50 pm by btorres4

» PURCHASE OF OTHER SUPPLIES FOR SB OFFICE
Wed Dec 13, 2017 4:51 pm by btorres4

» PURCHASE OF RICE FOR FOOD SUPPLIES OF PEACE & ORDER CAMPAIGN
Wed Dec 13, 2017 3:19 pm by btorres4

» Expired Tax Clearance during payment
Wed Dec 13, 2017 3:11 pm by vallemaco6224

» PURCHASE OF MEDICINE FOR MHO
Wed Dec 13, 2017 2:53 pm by btorres4


Contract time extension

View previous topic View next topic Go down

Contract time extension

Post by fe a. araya on Tue Jul 05, 2011 8:00 pm

Up to what % of the original contract time can we extend to a contractor who is requesting time extension due to unworkable weather condition? The original contract duration is 120 days and the contractor is requesting 60 days time extension
avatar
fe a. araya
Board Veteran
Board Veteran

Female Number of posts : 335
Company/Agency : DENR Region 5, Rawis, Legaspi City
Occupation/Designation : OIC, Adm. Division/BAC Secretariat
Registration date : 2009-08-20

Back to top Go down

Re: Contract time extension

Post by engrjhez® on Wed Jul 06, 2011 10:16 am

fe a. araya wrote:Up to what % of the original contract time can we extend to a contractor who is requesting time extension due to unworkable weather condition? The original contract duration is 120 days and the contractor is requesting 60 days time extension

I believe there are no specific guidelines on the extension of contract for as long as the prices remained fixed (no extra cost) and reasons justifiable enough. Please correct me if I missed something. Smile
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2481
Age : 39
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum