Annex "C" and Sec. 34.8 of the Revised IRR RA 9184 allows only 30 calendar days for the post qualification process in the procurement of goods. If a bidder has been determined as having the lowest calculated and responsive bid but the BAC does not act within the 30-day prescribed period, what is the legal effect of such inaction on the part of the BAC ? Is it estopped from issuing a ruling on the biding after 30 days ? study: