Post by accounting on Thu Feb 16, 2012 1:46 pm

We posted in philgeps an infra projects, the original is by administration, now the HOPE wishes to contract to bidders, what shall we do?
avatar
accounting
Active Poster
Active Poster

Male Number of posts : 84
Company/Agency : State Universities and Colleges
Occupation/Designation : Accountant III
Registration date : 2010-08-10

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by Jovinal on Thu Feb 16, 2012 9:06 pm

You will revised the Program of Work and Estimate from By Administration(Materials+Labor only) to Straight Contract(Materials+Labor+Profit) to Adjust the ABC and A Bac Resolution to Implement Infra Project through Straight Contract.
avatar
Jovinal
Board Veteran
Board Veteran

Male Number of posts : 438
Company/Agency : LGU- Danao City
Occupation/Designation : City Accountant
Registration date : 2011-11-27

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by alpha1 on Fri Feb 17, 2012 10:26 am

Greetings!
Just update your APP by changing the Mode of Procurement through a BAC Resolution from BY ADMINISTRATION to COMPETITIVE BIDDING. I think there is no need to revise the POW because it is just the same ABC only the mode of procurement was change.
avatar
alpha1
Active Poster
Active Poster

Male Number of posts : 145
Age : 54
Company/Agency : LGU
Occupation/Designation : Department Head
Registration date : 2010-03-12

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by Jovinal on Fri Feb 17, 2012 8:41 pm

The budgetary requirement for one infra project if implemented through STRAIGHT CONTRACT is higher than BY ADMINISTRATION, because in STRAIGHT CONTRACT you have to add the 20% FOR THE CONTRACTOR'S PROFIT. in addition to Materials and Labor Components in POWE. No contractor will accept the project without PROFIT.
avatar
Jovinal
Board Veteran
Board Veteran

Male Number of posts : 438
Company/Agency : LGU- Danao City
Occupation/Designation : City Accountant
Registration date : 2011-11-27

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by accounting on Sat Feb 18, 2012 9:42 am

ok tnx to all, this will really help
avatar
accounting
Active Poster
Active Poster

Male Number of posts : 84
Company/Agency : State Universities and Colleges
Occupation/Designation : Accountant III
Registration date : 2010-08-10

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by Jovinal on Sat Feb 18, 2012 12:57 pm

The problem there is when the original appropriation is not enough to cover the revised POWE.
avatar
Jovinal
Board Veteran
Board Veteran

Male Number of posts : 438
Company/Agency : LGU- Danao City
Occupation/Designation : City Accountant
Registration date : 2011-11-27

Back to top Go down

Re: Change of manner of execution of infra projects.

Post by Sponsored content


Sponsored content


Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum