Post by ruby buenaventura on Fri Feb 24, 2012 10:59 pm

Please make this clear for us: (Infrastructure Projects - IRR SECTION 62)
1. Do we need to secure a warranty security (Surety Bonds) @ 30% of the contract amount for projects completed from the date of completion to date of acceptance? Certificate of Completion at DPWH projects is being issued upon completion while Certificate of Acceptance is being issued after a year of completion.
2. Is the above warranty security (Surety Bonds) a requirement for final payment of the completed projects?
3. Do we still need to secure a ANOTHER warranty security (Surety Bonds @ 30% of Contract Amount)for a year from date of issuance of Certificate of Acceptance (or 1 year after project is completed)?
4. Do we still need to secure a warranty security (surety bond @ 30% of contract amount) if project is completed 2 or 3 years ago?
5. please... we need clarifications of IRR 62.2.

ruby buenaventura
New Member
New Member

Female Number of posts : 1
Company/Agency : houserock builders & trading
Occupation/Designation : project development officer
Registration date : 2012-02-24

Back to top Go down

Re: warranty security

Post by RDV @ GP3i on Sat Feb 25, 2012 7:47 am

ruby buenaventura wrote:Please make this clear for us: (Infrastructure Projects - IRR SECTION 62)
1. Do we need to secure a warranty security (Surety Bonds) @ 30% of the contract amount for projects completed from the date of completion to date of acceptance? Certificate of Completion at DPWH projects is being issued upon completion while Certificate of Acceptance is being issued after a year of completion.
Yes, you need to secure a warranty security after acceptance (1 year after completion.)

ruby buenaventura wrote:2. Is the above warranty security (Surety Bonds) a requirement for final payment of the completed projects?
Warranty Security is mandatory. It may not be a requirement for final payment, but maybe it is being used so that the contractor should post the required warranty security. It replaces the performance security you have posted.

ruby buenaventura wrote:3. Do we still need to secure a ANOTHER warranty security (Surety Bonds @ 30% of Contract Amount)for a year from date of issuance of Certificate of Acceptance (or 1 year after project is completed)?
Yes, because your performance security is good only from start of project until the issuance of certificate of acceptance. The warranty security will be good for one (1) year from acceptance.

ruby buenaventura wrote:4. Do we still need to secure a warranty security (surety bond @ 30% of contract amount) if project is completed 2 or 3 years ago?
5. please... we need clarifications of IRR 62.2.
No more, but it is still covered by the warranty period, so that, in case there is structural defect or structural failure on the project not caused by force majeure, you will still be responsible for those defects/failures even if it is no longer covered by any warranty security more than one (1) after acceptance.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: warranty security

Post by engrjhez® on Sat Feb 25, 2012 1:36 pm

I think a lot of people are confused about this. One of the questions: is the term "acceptance" be taken differently from "final acceptance"?. In the usual practice, the certificate of acceptance is being required prior to payment. I have my own interpretations though, that the correct case is either of the two:
1. That final acceptance is different from acceptance itself; or
2. They are just the same, and that acceptance should not be a requisite for payment but for the release of retention money.
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2480
Age : 38
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

Re: warranty security

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum