Contract Timeline for Particular Project

Post by Ken Uy on Fri Mar 23, 2012 4:54 pm

Hi to all,

Good day, tanung lang po regarding the contract, normally ba 3 years contracted for a particular project? eh paano kung 2 years lang valid pa ba yun? meron ba nakasaad sa ra9184 or sa ra7718? thank you in advance Smile

Ken Uy
New Member
New Member

Male Number of posts : 6
Company/Agency : DSource Inc.
Occupation/Designation : Head - Admin & Product Development Group
Registration date : 2012-03-23

Back to top Go down

Re: Contract Timeline for Particular Project

Post by RDV @ GP3i on Sat Mar 24, 2012 8:48 am

Ken Uy wrote:Hi to all,

Good day, tanung lang po regarding the contract, normally ba 3 years contracted for a particular project? eh paano kung 2 years lang valid pa ba yun? meron ba nakasaad sa ra9184 or sa ra7718? thank you in advance Smile

Ang normal term ng contract ay one (1) year lang. Maaari ang multi-year contract pero limited lang ang application nito, gaya ng security at janitorial services lang at dapat sa bidding process pa lang malinaw na gayon ang term. Maari din ang 2 years pero hindi pwede ang mahigit sa 3 taon.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Contract Timeline for Particular Project

Post by Ken Uy on Mon Mar 26, 2012 9:48 pm

Ok, how bout pag infrastructure na ang project, or consulting services na?

Ken Uy
New Member
New Member

Male Number of posts : 6
Company/Agency : DSource Inc.
Occupation/Designation : Head - Admin & Product Development Group
Registration date : 2012-03-23

Back to top Go down

Re: Contract Timeline for Particular Project

Post by Ken Uy on Mon Mar 26, 2012 9:53 pm

can u explain further more the multi year contract sir, and kung papanu naging limited and application nito, Thank you sir in advance Smile

Ken Uy
New Member
New Member

Male Number of posts : 6
Company/Agency : DSource Inc.
Occupation/Designation : Head - Admin & Product Development Group
Registration date : 2012-03-23

Back to top Go down

Re: Contract Timeline for Particular Project

Post by RDV @ GP3i on Tue Mar 27, 2012 7:07 am

Ken Uy wrote:can u explain further more the multi year contract sir, and kung papanu naging limited and application nito, Thank you sir in advance Smile

Generally, contracts should be completed within one (1) year only, whether that be contracts for the procurement of goods and services, infrastructure projects, or consulting services.The same is true for the procurement of janitorial and security services. In the latter case, while contract for these kind of services should be completed in one (1) year, those kind of services are normally of a continuing nature and it may not be cost-beneficial if a procuring entity would be conducting a competitive bidding and entering into a new contract every year.

Likewise, the funding source for a project or the Approve Budget for the Contract (ABC) is also appropriated for a period of one (1) year only. It cannot, therefore, be used to fund a contract that extends beyond a one-year period. The procuring entity will need a multi-year obligational authority for the purpose.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Contract Timeline for Particular Project

Post by Ken Uy on Tue Mar 27, 2012 9:53 am

Hi Sir,

Thank you for the informative answer. Smile

Ken Uy
New Member
New Member

Male Number of posts : 6
Company/Agency : DSource Inc.
Occupation/Designation : Head - Admin & Product Development Group
Registration date : 2012-03-23

Back to top Go down

Re: Contract Timeline for Particular Project

Post by Alpha on Tue Mar 27, 2012 2:59 pm

For infrastructure, the timeline of a certain project will depend on its scope of works. Normally, small projects can be programmed for even less than a year while most large projects can consume longer periods of time. There are cases where projects can go for two years or more.

From another view, the usual trend a project can be accomplished also have significant relationship with the total contract cost. As can be observed from small, medium, or large projects, the higher the cost, the more the scope of works, the longer period covered. Statistics, however, can show more accurate figures.

Alpha
Active Poster
Active Poster

Male Number of posts : 53
Company/Agency : Private Sector
Occupation/Designation : Project Supervisor
Registration date : 2011-07-28

Back to top Go down

Re: Contract Timeline for Particular Project

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum