Approval of the PPMP, APP and BAC Resolution

Post by riddler on Fri Jul 17, 2009 10:34 am

Since the Program Holders/End-Users has already indicated their Mode of Procurements (Competitive or Alternative) and consolidated by the BAC/BAC-Secretariat through the APP, does the APP needs a BAC Resolution recommending the same to the HOPE?
avatar
riddler
Board General
Board General

Male Number of posts : 598
Company/Agency : lgu
Occupation/Designation : endyeenel
Registration date : 2009-03-03

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by RDV @ GP3i on Fri Jul 17, 2009 10:54 am

ruel wrote:Since the Program Holders/End-Users has already indicated their Mode of Procurements (Competitive or Alternative) and consolidated by the BAC/BAC-Secretariat through the APP, does the APP needs a BAC Resolution recommending the same to the HOPE?

The end-users indicate their preference for the mode of procurement in their PPMPs.

It is, however, the responsibility of the BAC, through the BAC Secretariat, to consolidate the PPMPs to the APP. In the consolidated APP, the mode of procurement as recommended by the BAC, may no longer be the preferred mode by the end-user (for a number of reasons). The APP then has to be approved by the HOPE, upon recommendation by the BAC. The BAC recommendation has to be in the form of a BAC Resolution.

Therefore, the answer to your question, engr ruel, is a definite YES.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by riddler on Fri Jul 17, 2009 11:14 am

RDV wrote:
ruel wrote:Since the Program Holders/End-Users has already indicated their Mode of Procurements (Competitive or Alternative) and consolidated by the BAC/BAC-Secretariat through the APP, does the APP needs a BAC Resolution recommending the same to the HOPE?

The end-users indicate their preference for the mode of procurement in their PPMPs.

It is, however, the responsibility of the BAC, through the BAC Secretariat, to consolidate the PPMPs to the APP. In the consolidated APP, the mode of procurement as recommended by the BAC, may no longer be the preferred mode by the end-user (for a number of reasons). The APP then has to be approved by the HOPE, upon recommendation by the BAC. The BAC recommendation has to be in the form of a BAC Resolution.

Therefore, the answer to your question, engr ruel, is a definite YES.

OK. Thanks RDV.
avatar
riddler
Board General
Board General

Male Number of posts : 598
Company/Agency : lgu
Occupation/Designation : endyeenel
Registration date : 2009-03-03

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by sunriser431 on Mon Jul 20, 2009 12:00 am

Our is different, each department would prepare their own budget (fully supported with PPMPs) after deliverations for each Department Budget, the Governing Board would issue Board resolutions approving the respective department Budget. as for the BAC, their functions would be the implementation of the projects,( conduct biddings in accordance with GPRA.)
avatar
sunriser431
Grand Master
Grand Master

Male Number of posts : 1518
Company/Agency : Goccs Jolo Sulu All the way Downsouth
Occupation/Designation : IAS
Registration date : 2009-05-07

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by riddler on Mon Jul 20, 2009 10:56 am

sunriser431 wrote:Our is different, each department would prepare their own budget (fully supported with PPMPs) after deliverations for each Department Budget, the Governing Board would issue Board resolutions approving the respective department Budget. as for the BAC, their functions would be the implementation of the projects,( conduct biddings in accordance with GPRA.)

which in this case, maybe contrary to what RDV suggested, that the mode of procurement in the APP must have a BAC resolution.
avatar
riddler
Board General
Board General

Male Number of posts : 598
Company/Agency : lgu
Occupation/Designation : endyeenel
Registration date : 2009-03-03

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by RDV @ GP3i on Mon Jul 20, 2009 11:04 am

sunriser431 wrote:Our is different, each department would prepare their own budget (fully supported with PPMPs) after deliverations for each Department Budget, the Governing Board would issue Board resolutions approving the respective department Budget. as for the BAC, their functions would be the implementation of the projects,( conduct biddings in accordance with GPRA.)

Based on Corporate Operating Budget (COB) approved by the Board, the department departments will have to update their PPMPs, particularly if there were changes from the ones proposed. The BAC's responsibility is not only the "implementation" of the projects (which I suppose is to conduct procurement activities/bidding process), but should consolidate the various PPMPs into the APPs. It is the responsibility of the BAC also to recommend the mode of procurement, which should be indicated in the APP. As I posted earlier, the preferred mode of procurement by the end-users or department heads may not necessarily be the one recommended by the HOPE. In the case of GOCCs, the HOPE is the governing board, but normally it is the General Manager/CEO/President that is the approving authority.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by leobcaleja on Wed Jun 18, 2014 2:39 pm

"In the case of GOCCs, the HOPE is the governing board, but normally it is the General Manager/CEO/President that is the approving authority."

Can I have a reference on this? I was informed that the instruction from the GM of a GOCC is invalid unless the said instruction is approved by the HOPE.
avatar
leobcaleja
New Member
New Member

Male Number of posts : 49
Company/Agency : hanjin heavy industries and const. co., ltd.
Occupation/Designation : chief office engineer
Registration date : 2010-09-19

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by esmeeardona on Wed Jun 18, 2014 4:25 pm

How about if the unit is project based, as in funding comes in tranches. How do you go about the preparation of the PPMP?

esmeeardona
New Member
New Member

Female Number of posts : 1
Company/Agency : NTHC, UP manila
Occupation/Designation : Project assistant
Registration date : 2014-06-10

Back to top Go down

Re: Approval of the PPMP, APP and BAC Resolution

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum