DENR PENRO Rizal Antipolo City- PROCUREMENT OF SURVEY, MAPPING AND PLANNING (SMP), PRODUCTION/PROCUREMENT OF QUALITY SEEDLINGS AND SITE PREPARATION THRU COMMUNITY PARTICIPATION/SHOPPING FOR THE FOLLOWING:

View previous topic View next topic Go down

DENR PENRO Rizal Antipolo City- PROCUREMENT OF SURVEY, MAPPING AND PLANNING (SMP), PRODUCTION/PROCUREMENT OF QUALITY SEEDLINGS AND SITE PREPARATION THRU COMMUNITY PARTICIPATION/SHOPPING FOR THE FOLLOWING:

Post by PENRO RIZAL on Tue Jul 24, 2012 3:38 pm

A. National Convergence Initiative (NCI) Plantation Establishment
located at So. Alas-asin, Brgy. Daraitan, Tanay Rizal
1. Survey Mapping and Planning
Target------------------------ 118 has.
Unit Cost--------------------- 900.00
Approved Budget Cost---------- P106,200.00
2. Procurement/Production of Fruit bearing,seedlings
(cacao, coffee, guyabano,atis, langka, Avocado, etc.)
Target--------------------------59,000 seedlings
Unit Cost----------------------- 20.00
Approved Budget---------------- P1,180,000.00
3. Site Preparation (strip brushing to planting)
Target-------------------------- 118 has.
Unit Cost ----------------------- 2,500.00
Approved Budget ----------------P 295,000.00
B. FMS-DA Target- Plantation Establishment located at
Brgy. Mamuyao Tanay, Rizal
1. Procurement/Production of Fruit Bearing Seedlings
(Guyabano, Atis, Langka, Anonas etc.)
Target ------------------ 51,250 seedlings
Unit Cost---------------- 20.00
Approved Budget--------- P 1,025,000.00
2. Procurement of forest trees seedlings acacia
Target--------------------10,000 seedlings
Unit Cost----------------- 12.00
Approved Budget---------- 120,000.00
3. Site Preparation (Strip brushing to Planting)
Target -------------------122.50 has.
Unit Cost ----------------2,500
Approved Budget--------- P 306,250.00

TOTAL-------------------P 3,032,450.00

C. Upper Marikina River Basin Protected Landscape (UMRBPL)
1. Procurement/Production of forest tree seedlings
(kupang 5' over So. San Ysiro Brgy. San Jose Antipolo City
Target------------------45,000 seedlings
Unit Cost--------------- 15.00
Approved Budget-------- 675,000.00


Last edited by DENR-PENRO RIZAL on Tue Jul 24, 2012 4:04 pm; edited 1 time in total (Reason for editing : additional)

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15