Abstract as read or abstract as computed

View previous topic View next topic Go down

Abstract as read or abstract as computed

Post by stephen on Sat Aug 04, 2012 5:01 pm

sir,

tanong ko lang po kung saan po dito yung magiging bid po ng bidder?
Sa abstract as read po ba o sa abstract as computed?
Ano po ba yung sinasabing "beneficial to the government"?
thanks po..

stephen
New Member
New Member

Male Number of posts : 38
Company/Agency : DepEd
Occupation/Designation : twg
Registration date : 2011-04-01

Back to top Go down

Re: Abstract as read or abstract as computed

Post by RDV @ GP3i on Sat Aug 04, 2012 11:55 pm

stephen wrote:sir,

tanong ko lang po kung saan po dito yung magiging bid po ng bidder?
Sa abstract as read po ba o sa abstract as computed?
Ano po ba yung sinasabing "beneficial to the government"?
thanks po..

Pareho bid ng bidder ang bid as read at ang bid as calculated (or bid as computed, sabi mo nga). Ang abstract of bid as read ay ginagawa pagkatapos ng bid opening, base yun sa kung magkano ang bid price ng bidder ng ito ay binasa ng BAC.

Pagkatapos ng bid opening, ang sunod na step ay bid evaluation. Dito Naman ay kino-compute o kina-calculate ng BAC kung tama ba ang pagkakakwenta ng bidder ng kanyang bid price. Kung meron Mali sa kwenta, gaya ng maling addition o multiplication, Ito ay itatama na BAC. Ang taming bid price Naman ang ilalagay sa abstract of bid as calculated.

Ang calculated bid prices ang pagsusunodsunurin mula sa pinakamababang presyo (rank from lowest calculated to highest). Ang pinakamababa ang idadaan sa post-qualification process. Dahil yun ang pinakamababa, yun ang pinaka advantageous price sa govt.

Sa pag award Naman ng kontrata sa LCRB, Kung ang kanyang bid as read ay mas mababa sa kanyang bid as calculated, dapat ang presyo ng kanyang kontrata ay hanggang sa bid as read lang kasi iyun ay mas beneficial din sa gobyerno at dahil yun din ang sinasaad ng RA 9184 at IRR.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Abstract as read or abstract as computed

Post by stephen on Sun Aug 05, 2012 7:38 pm

sir,

kung mas masmataas ang computed po, paano po gagawin ang variation order base dun sa bid nya po
kung gagamitin natin yung abstract as read? ipapaayos po ba namin yung bid ng bidder para lang tumama
sa abstract as read yung bid nya?
thanks po..

stephen
New Member
New Member

Male Number of posts : 38
Company/Agency : DepEd
Occupation/Designation : twg
Registration date : 2011-04-01

Back to top Go down

Re: Abstract as read or abstract as computed

Post by RDV @ GP3i on Sun Aug 05, 2012 7:55 pm

stephen wrote:sir,

kung mas masmataas ang computed po, paano po gagawin ang variation order base dun sa bid nya po
kung gagamitin natin yung abstract as read? ipapaayos po ba namin yung bid ng bidder para lang tumama
sa abstract as read yung bid nya?
thanks po..

Kailangan muna na ipatama nya ang BOQ o detailed estimate sa presyo ng kontrata para ito ang magiging basehan kung meron mang variation order na kailangan.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: Abstract as read or abstract as computed

Post by stephen on Sun Aug 05, 2012 9:22 pm

thanks po sa info sir..
God bless po at mabuhay po kayo..

stephen
New Member
New Member

Male Number of posts : 38
Company/Agency : DepEd
Occupation/Designation : twg
Registration date : 2011-04-01

Back to top Go down

Re: Abstract as read or abstract as computed

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum