Compute for your Procurement Timelines using GPPB Beta App

Post by engrjhez® on Sat Dec 22, 2012 1:00 pm

Here is a link to compute for the earliest and latest allowable periods of procurement for Goods, Infrastructure Projects and Consulting Services*.

http://www.gppb.gov.ph/timelines/timelines.htm

However, I do not agree with some results:

  1. The advertisement period for Goods and Infra is only 7 days. Consistent with the principle of competitiveness (Sec.3.b of the IRR), availability of Bidding Documents (under Sec.17.3 of the IRR) and the posting requirement of the PhilGEPS (www.philgeps.gov.ph) , I respectfully submit that is must be from Day 1 until the deadline for submission and receipt of bids.

  2. If pre-bid conference is not mandatory, like in the cases ABC=P1M and below, the procurement timeline is EARLIER than the earliest possible period allowed under Annex "C" of the IRR. It appears like that the schedule of Public Bidding is reduced to the timelines of Alternative Methods of Procurement.

  3. The app does not distinguish non-working days. It is understandable however that it is still in its beta stage.

I hope the GPPB-TSO can clarify these matters to avoid confusion. Smile

*still under construction as of 22 Dec 2012
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2480
Age : 39
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum