Preparation of Abstract of Bids as Calculated under Negotiated Procurement after 2 failed bidding

View previous topic View next topic Go down

Preparation of Abstract of Bids as Calculated under Negotiated Procurement after 2 failed bidding

Post by Jovinal on Tue Sep 17, 2013 9:00 pm

I just like to ask a clarification if under the Negotiated Procurement after 2 failed biddings the following steps are necessary:

1) preparation of Abstract of bids as Calculated
2) Ranking of LCRB
3) Post qualification

Trank You.
avatar
Jovinal
Board Veteran
Board Veteran

Male Number of posts : 438
Company/Agency : LGU- Danao City
Occupation/Designation : City Accountant
Registration date : 2011-11-27

Back to top Go down

Re: Preparation of Abstract of Bids as Calculated under Negotiated Procurement after 2 failed bidding

Post by regina avelino on Wed Sep 18, 2013 12:27 pm

Per Generic Procurement Manual

"If the procurement is being negotiated because of two previous failures of bidding or in case of imminent danger to life or property, the BAC, through the BAC Secretariat, issues invitations to at least three (3) suppliers of good standing for the latter to negotiate a contract. The Procuring Entity may draw these suppliers from its list of registered suppliers. The procedures for the conduct of public bidding should be observed. However, the minimum period for each bidding procedure may be reduced."

regina avelino
Board General
Board General

Female Number of posts : 663
Company/Agency : gocc ncr
Occupation/Designation : staff