Question sir/mam ask ko lang po meron kami ipapabidding na project amounting to 57million which is a loan from a government bank ang project is construction of public market.

my question is how long does it takes for us to publish sa philgeps ang invitation to bid of that project? ok lang po ba ang 14 calendar days? tapos after 14 cd ilang days bago kami makapagpabid?

ok lang po ba na just for example posting date is Oct 22 - Nov. 04, 2013 (14CD) pede na po ba kami magpa bid ng November 08, 2013? tapos ang post qua ay Nov. 11-15, 2013 (5CD) then award namin ng November 20?

need your inputs..thanks

alvinambion
New Member
New Member

Male Number of posts : 42
Age : 36
Company/Agency : Municipal Government of Amadeo, Cavite
Occupation/Designation : Administrative Aide VI
Registration date : 2011-05-12

Back to top Go down

Re: HELP! po....

Post by njimenez on Wed Nov 13, 2013 2:36 pm

pls refer to Annex C of the revised IRR of r.a. 9184 (period of procurement activities)

njimenez
New Member
New Member

Male Number of posts : 25
Company/Agency : LGU-San Miguel
Occupation/Designation : Municipal Engineer/BAC Chairman
Registration date : 2012-02-20

Back to top Go down

Re: HELP! po....

Post by regina avelino on Thu Nov 14, 2013 11:20 am

below is the best that you can do.  posting is only 7 days.


Stage---------------------Start----------- End
advertisement-----------10/22/13-----10/29/13
Prebid--------------------10/30/13-----10/30/13
bid submission----------11/11/13-----11/11/13
bid evaluation-----------11/12/13-----11/12/13
post-qua-----------------11/13/13-----11/15/13
NOA----------------------11/19/13-----11/20/13
contract signing---------11/21/13-----11/22/13
approval-----------------11/23/13----- 11/23/13
NTP----------------------11/25/13-----11/25/13

regina avelino
Board General
Board General

Female Number of posts : 671
Company/Agency : gocc ncr
Occupation/Designation : staff
Registration date : 2012-02-15

Back to top Go down

Re: HELP! po....

Post by Abecedarian on Fri Nov 15, 2013 12:32 pm

Go to GPPB Website, click procurement timelines to compute the dates for each stage of your public bidding activity.
avatar
Abecedarian
Active Poster
Active Poster

Male Number of posts : 145
Company/Agency : Philippine Postal Corporation, Area VII
Occupation/Designation : Administrative Officer III
Registration date : 2011-04-08

Back to top Go down

Re: HELP! po....

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top


 
Permissions in this forum:
You cannot reply to topics in this forum