NEW PLANTATION ESTABLISHMENT CY 2014 AT VILLAGE EAST SUBDIVISION BRGY. STO DOMINGO CAINTA, RIZAL

Go down

NEW PLANTATION ESTABLISHMENT CY 2014 AT VILLAGE EAST SUBDIVISION BRGY. STO DOMINGO CAINTA, RIZAL

Post by PENRO RIZAL on Wed Oct 15, 2014 3:05 pm

[b]Seedlings Production[/b]

Seedlings- Classified as saplings

target- 400
unit cost -75.00
cost per has.- 30,000

Plantation Establishment
B.1 Strip brushing (1meter width)

target- 4
unit cost- 2.50
cost per ha.- 1,000
B.2 Hole digging (6 inches deep & 6 inches in diam)

target - 400
unit cost - 1.25
cost per ha.- 500
B.3 Stakes (2.5 feet)

target - 400
unit cost - 1.00
cost per ha.- 400
B.4 Hauling
target - 400
unit cost - 1.25
cost per ha.- 500
B.5 Actual Planting (4mx5m spacing)
target - 400
unit cost - 1.25
cost per ha.- 600

[b]TOTAL COST------------33,000.00[/b]

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15

Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum