[b]Seedlings Production[/b]

Seedlings- Classified as saplings

target- 400
unit cost -75.00
cost per has.- 30,000

Plantation Establishment
B.1 Strip brushing (1meter width)

target- 4
unit cost- 2.50
cost per ha.- 1,000
B.2 Hole digging (6 inches deep & 6 inches in diam)

target - 400
unit cost - 1.25
cost per ha.- 500
B.3 Stakes (2.5 feet)

target - 400
unit cost - 1.00
cost per ha.- 400
B.4 Hauling
target - 400
unit cost - 1.25
cost per ha.- 500
B.5 Actual Planting (4mx5m spacing)
target - 400
unit cost - 1.25
cost per ha.- 600

[b]TOTAL COST------------33,000.00[/b]

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum