Approved Budget for the Contract and Actual Total Itemized Amount

Post by gherzy27 on Mon Jan 05, 2015 5:49 am

Hi All,

Which prevails, the approved budget for the contract OR the total actual itemized amount in the purchase request

gherzy27
New Member
New Member

Male Number of posts : 19
Company/Agency : none
Occupation/Designation : none
Registration date : 2011-07-28

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by gherzy27 on Mon Jan 05, 2015 7:42 am

The total actual amount for each item is higher than the ABC. Which of the two amount shall be considered by the BAC

gherzy27
New Member
New Member

Male Number of posts : 19
Company/Agency : none
Occupation/Designation : none
Registration date : 2011-07-28

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by gherzy27 on Mon Jan 05, 2015 7:46 am

Can the provision on the variance between total bid price and itemized pricing be applied?

gherzy27
New Member
New Member

Male Number of posts : 19
Company/Agency : none
Occupation/Designation : none
Registration date : 2011-07-28

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by artlayug on Thu Jan 08, 2015 3:02 pm

gherzy27 wrote:Hi All,

Which prevails, the approved budget for the contract OR the total actual itemized amount in the purchase request

calculated amount which ever is lower

artlayug
New Member
New Member

Male Number of posts : 2
Company/Agency : Commission On Audit
Occupation/Designation : Service Chief
Registration date : 2012-09-28

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by engrjhez® on Fri Jan 09, 2015 11:17 am

gherzy27 wrote:Hi All,

Which prevails, the approved budget for the contract OR the total actual itemized amount in the purchase request

It is the ABC. Purchase request should follow the ABC. The ABC is the basis for procurement, not the PR.
avatar
engrjhez®
Grand Master
Grand Master

Male Number of posts : 2480
Age : 39
Company/Agency : City Government of Bacoor [Region IV-A, Province of Cavite]
Occupation/Designation : Office of the City Legal Service (OCLS) / Certified National Trainer - PhilGEPS
Registration date : 2008-10-31

http://www.bacoor.gov.ph

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by Guest on Tue Jan 27, 2015 3:34 pm

ABC, if the undertaking will be awarded as a lot. The itemized amount in the PR is only a guide for the Agency in determining the ABC.

Guest
Guest


Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by jonred on Sat Mar 28, 2015 3:17 pm

Amount in purchase request should not be more than the approved budget for contract. Otherwise it is a violation of law I think.

jonred
New Member
New Member

Male Number of posts : 5
Company/Agency : Jonred trading
Occupation/Designation : Owner
Registration date : 2015-03-28

Back to top Go down

Re: Approved Budget for the Contract and Actual Total Itemized Amount

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum