Latest topics
» No Objection Letter
Yesterday at 5:21 pm by zeph03

» CATERING SERVICES FOR CONGRESSIONAL MEET AT SAGBAYAN, BOHOL
Thu Dec 14, 2017 7:14 pm by btorres4

» PURCHASE OF FERTILIZERS FOR LIVESTOCK, CORN, HVCDP, INLAND FISHERY, AND ORGANIC PROGRAM
Thu Dec 14, 2017 4:35 pm by btorres4

» Newspaper Publication
Thu Dec 14, 2017 4:10 pm by btorres4

» RENTAL OF LIGHTS AND SOUND SYSTEM
Thu Dec 14, 2017 3:46 pm by btorres4

» Newspaper Publication
Wed Dec 13, 2017 9:50 pm by btorres4

» PURCHASE OF OTHER SUPPLIES FOR SB OFFICE
Wed Dec 13, 2017 4:51 pm by btorres4

» PURCHASE OF RICE FOR FOOD SUPPLIES OF PEACE & ORDER CAMPAIGN
Wed Dec 13, 2017 3:19 pm by btorres4

» Expired Tax Clearance during payment
Wed Dec 13, 2017 3:11 pm by vallemaco6224

» PURCHASE OF MEDICINE FOR MHO
Wed Dec 13, 2017 2:53 pm by btorres4


prolonged suspension

View previous topic View next topic Go down

prolonged suspension

Post by pedro fudalan on Thu Jun 25, 2015 6:48 am

our project which has a contract duration of 120 cd has been suspended for more than 200 cd due to erroneous data reflected in the plans (e.g. elevations) and was resumed last nov 2014 and once again, was suspended for almost 90 days and was resumed last march 2015, however until today, the variation order due to changes in the plans is still on process. The program is about to expire this coming july 2015 and our accomplishment as of today is less than 50%. My question is, are we still entitled for a mutual termination due to the aforementioned circumstances despite the fact that we failed to inform the PE in writing, regarding our intention for a mutual termination? thank you.

pedro fudalan
New Member
New Member

Male Number of posts : 1
Company/Agency : private
Occupation/Designation : project engineer
Registration date : 2015-06-25

Back to top Go down