AWARDING OF CONTRACTS FOR THE CONSTRUCTION OF HANGING BRIDGE GOING TO PAMITINAN CAVE SITIO WAWA, BRGY. SAN RAFAEL, RODRIGUEZ, RIZAL

View previous topic View next topic Go down

AWARDING OF CONTRACTS FOR THE CONSTRUCTION OF HANGING BRIDGE GOING TO PAMITINAN CAVE SITIO WAWA, BRGY. SAN RAFAEL, RODRIGUEZ, RIZAL

Post by PENRO RIZAL on Tue Jul 21, 2015 3:06 pm

Construction of Hanging Bridge going to Pamitinan Cave

I. General Requirements
  a. Administrative Requirements ------------- P 22,462.00
  b. Temporary Facilities -----------------------    36,040.00
  c. Temporary Supply of Electricity ------------   25,000.00

II. Earth Works ------------------------------------ 160,000.00
III. Form Works ------------------------------------ 99,500.00
IV. Concrete Works -------------------------------- 427,600.00
V. Steel Works ------------------------------------- 831,893.00
VI. Installation of Wood
    Plastic Composite Works ----------------------- 397,505.00


Approved Budget Cost ----------------------------- P 2,000,000

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum