DESCRIPTION QTY UNIT COST AMOUNT
1. Mobilization 1 lot 10,000.00/lot 10,000.00
2. Bunkhouse 64 sq.m. 312.50/sq.m. 20,000.00
3. Site Clearing/Layout 1,120 sq.m. 31.25/sq.m. 35,000.00
4. Excavation 13.07 cu.m. 1,912.78/cu.m. 25,000.00
5 Concrete Works
5.1 Column/Wall Footing 4.35 cu.m. 3,448.28/cu.m. 15,000.00
5.2 Column 3.24 cu.m. 4,629.63/cu.m. 15,000.00
5.3 Walling 58.50 sq.m. 170.94/sq.m. 10,000.00
5.4 Flooring 120 sq.m. 166.67/sq.m. 20,000.00
5.5 Beam 2.55 cu.m. 5,882.35/cu.m. 15,000.00
5.6 Pavement 650 sq.m. 53.85/sq.m. 35,000.00
5.7 Finishing 145.80 sq.m. 68.59/sq.m. 10,000.00
6. Steel Works
6.1 Truss/Purlins 1 lot 35,000.00/lot 35,000.00
6.2 Railings 1 lot 5,000.00/lot 5,000.00
7. Roofing 252 sq.m. 119.05/sq.m. 30,000.00
8. Plumbing Works
8.1 Septic Tank/Vault 3.24 cu.m. 2,314.81/cu.m. 7,500.00
8.2 Plumbing Lines/Fixtures 1 lot 30,000.00/lot 30,000.00
9. Electrical Works 1 lot 30,000.00/lot 30,000.00
10. Tile Works 38.40 sq.m. 260.42/sq.m. 10,000.00
11. Painting Works 397.80 sq.m. 43.99/sq.m. 17,500.00
12. Landscaping 350 sq.m. 57.14/sq.m. 20,000.00
13. Demobilization 1 lot 10,000.00/lot 10,000.00

TOTAL APPROVED BUDGET = P 405,000.00

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum