AWARDING OF CONTRACTS FOR PLANTATION ESTABLISHMENT OF 150 HECTARES PIONEERING SPECIES PLANTATION UNDER NGP SUPPLEMENTAL TARGET CY 2015 AT BRGY. PURAY, RODRIGUEZ, RIZAL

View previous topic View next topic Go down

AWARDING OF CONTRACTS FOR PLANTATION ESTABLISHMENT OF 150 HECTARES PIONEERING SPECIES PLANTATION UNDER NGP SUPPLEMENTAL TARGET CY 2015 AT BRGY. PURAY, RODRIGUEZ, RIZAL

Post by PENRO RIZAL on Wed Aug 26, 2015 1:40 pm

ITEM QTY UNIT COST TOTAL COST
1. Seedling Production/Procurement 129,400 5.00 647,000.00
Pioneering Species
(5% mortality)

2. Labor
Strip Brushing 1,106 250.00 276,500.00
Hole digging 129,400 .50 64,700.00
Staking 129,400 .50 64,700.00
Hauling 129,400 1.00 129,400.00
Actual Planting 129,400 .50 64,700.00

3. First Year Maintenance and Protection
Re-strip brushing 150 284.33 42,650.00
Re-planting of seedlings (10% mortality) 12,940 5.00 64,700.00
Continuous patrol works 150 284.33 42,650.00

APPROVED BUDGET COST = P 1,397,000.00

PENRO RIZAL
Valued Contributor
Valued Contributor

Female Number of posts : 201
Company/Agency : DENR-PENRO RIZAL
Occupation/Designation : PLANNING OFFICER II
Registration date : 2012-05-15

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum