Latest topics
» No Objection Letter
Sat Dec 16, 2017 5:21 pm by zeph03

» CATERING SERVICES FOR CONGRESSIONAL MEET AT SAGBAYAN, BOHOL
Thu Dec 14, 2017 7:14 pm by btorres4

» PURCHASE OF FERTILIZERS FOR LIVESTOCK, CORN, HVCDP, INLAND FISHERY, AND ORGANIC PROGRAM
Thu Dec 14, 2017 4:35 pm by btorres4

» Newspaper Publication
Thu Dec 14, 2017 4:10 pm by btorres4

» RENTAL OF LIGHTS AND SOUND SYSTEM
Thu Dec 14, 2017 3:46 pm by btorres4

» Newspaper Publication
Wed Dec 13, 2017 9:50 pm by btorres4

» PURCHASE OF OTHER SUPPLIES FOR SB OFFICE
Wed Dec 13, 2017 4:51 pm by btorres4

» PURCHASE OF RICE FOR FOOD SUPPLIES OF PEACE & ORDER CAMPAIGN
Wed Dec 13, 2017 3:19 pm by btorres4

» Expired Tax Clearance during payment
Wed Dec 13, 2017 3:11 pm by vallemaco6224

» PURCHASE OF MEDICINE FOR MHO
Wed Dec 13, 2017 2:53 pm by btorres4


Deficiency in quantities and scope of work

View previous topic View next topic Go down

Deficiency in quantities and scope of work

Post by igno1984 on Thu Oct 01, 2015 8:47 am

When an infra project was being negotiated under on-going contracts and upon proposals evaluation the contractor requested that the works shall be amended because the quantities for some items were inaccurate base on ocular inspection, what shall be the next move of the BAC? Comments please, thanks!

igno1984
New Member
New Member

Male Number of posts : 4
Company/Agency : Bicol University - GASS
Occupation/Designation : BAC Secretariat
Registration date : 2015-10-01

Back to top Go down