Partial Acceptance of Award after Bid Validity Period

View previous topic View next topic Go down

Partial Acceptance of Award after Bid Validity Period

Post by Dave Jubilado on Tue Oct 27, 2015 11:06 am

Good day.
Our Agency conducted a bidding for construction materials sometime in March 2015, however the award was made only in July due to the delay in the releasing of our SAA from the DBM. The supplier informed us in writing that he can no longer accept the award since his bid offer is no longer valid. However, he expressed his willingness to still accept the award for all other items except for one (cement) due to price escalation. In the exigency of the service, can we still issue the award for all other items except for cement and conduct a re-bidding for that item alone, or should we go to through the process of public bidding again for all the items being procured?



Dave Jubilado
New Member
New Member

Male Number of posts : 2
Company/Agency : National Irrigation Administration R.O. IX
Occupation/Designation : Chief Corporate Accountant B
Registration date : 2015-10-22

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum