Post by countme_in18 on Fri Nov 27, 2015 1:05 pm

The procuring entity issued last september 7, 2015 a NOA and we posted a performance bond 3 days after. The contract and NTP was issued last November 19, 2015. Upon checking, stocks we offered was already phase out and offering the new equivalent model but the entity refuse to accept the offer. Now in section 37.2 of the Implementing Rule and Regulation of Republic Act No. 9184 that the entity shall enter into contract within 10 the same day from the issuance of NOA.

The NTP was 72 days delayed as prescribe in IRR 37.2 from the issuance of NOA and I know the entity has no valid reason in the delays kasi lahat ng documents is ok na as per bac member advised at kulang nalng ng signature ng Director ( matagal na pirmahan)

Question: Can the entity blacklist us if hindi namin ma deliver yung computer model na offer namin kasi phase out na? And ano po defense namin doon? can we refuse to accept the NTP kasi beyond 10 days delay na po yung issuance of NTP
avatar
countme_in18
New Member
New Member

Male Number of posts : 11
Company/Agency : Columbia
Occupation/Designation : Account Executive
Registration date : 2010-09-21

Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum