Post by lowie on Thu Jan 19, 2017 7:25 pm

hello... may i seek everyone's help on my inquiry about 15% advance payment for infrastructure......... Suppose, the contractor claims cash advance beyond the prescribed period after the signing of contract, is he still allowed to claim advance payment? please guys help me on this topic.....
avatar
lowie
New Member
New Member

Female Number of posts : 15
Company/Agency : LGU - Municipality of Socorro
Occupation/Designation : BAC Member
Registration date : 2009-09-07

Back to top Go down

Re: when to release the 15% advance payment for project construction

Post by leobcaleja on Fri Jan 20, 2017 10:22 am

As long as the contractor has complied with the requirements for the release of the advance payment.
avatar
leobcaleja
New Member
New Member

Male Number of posts : 49
Company/Agency : hanjin heavy industries and const. co., ltd.
Occupation/Designation : chief office engineer
Registration date : 2010-09-19

Back to top Go down

Re: when to release the 15% advance payment for project construction

Post by lowie on Fri Jan 20, 2017 10:46 am

What if the claim is done 7 months after the signing of the contract, that instead of progress payment, advance payment is being claimed by the contractor?
avatar
lowie
New Member
New Member

Female Number of posts : 15
Company/Agency : LGU - Municipality of Socorro
Occupation/Designation : BAC Member
Registration date : 2009-09-07

Back to top Go down

Re: when to release the 15% advance payment for project construction

Post by leobcaleja on Fri Jan 20, 2017 4:57 pm

So after 7 months the contractor has not billed any progress payment? Is there a problem in the implementation of the project?

Usually there is a period of recoupment for the advance payment and the advance payment must be covered by a bond.
avatar
leobcaleja
New Member
New Member

Male Number of posts : 49
Company/Agency : hanjin heavy industries and const. co., ltd.
Occupation/Designation : chief office engineer
Registration date : 2010-09-19

Back to top Go down

Re: when to release the 15% advance payment for project construction

Post by Sponsored content


Sponsored content


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum